Construction & development financing
Construction liens are financing risk because they can affect cash today, mortgage priority during the build and title at the permanent takeout
Ontario construction lien law changes the cash and priority environment around every construction advance. Borrowers need to distinguish statutory holdback from lender retentions and understand why lien/title clearance can control both draws and permanent refinancing.
Construction liens affect cash, title and mortgage priority—not only disputes between contractors
Ontario’s Construction Act gives qualifying persons who supply services or materials to an improvement statutory lien rights. For a borrower, that means unpaid construction obligations can become a title and financing problem even where the property value is strong.
A construction lender may therefore require evidence about contractor payments, statutory holdbacks, lien status and title before advancing or taking out the construction mortgage.
Ontario’s basic statutory holdback is 10%—but the legal calculation belongs to the Construction Act
Current section 22 of Ontario’s Construction Act requires a payer under a contract or subcontract under which a lien may arise to retain a basic holdback equal to 10% of the price of the services or materials as they are actually supplied under the contract or subcontract.
That statutory holdback is part of the construction-payment chain. It is not the same thing as a lender’s contractual draw holdback, a construction contingency, an interest reserve or money the borrower informally keeps “just in case.”
| Amount | Purpose | Who controls the rule |
|---|---|---|
| Construction Act statutory holdback | Statutory protection within construction payment/lien regime | Ontario Construction Act |
| Lender draw retention | Protect completion, deficiencies, documentation or lender conditions | Construction loan agreement |
| Contingency | Pay unforeseen project cost | Project budget / lender requirements |
| Interest reserve | Fund construction-period financing cost where structured | Loan agreement / project budget |
The holdback regime changed materially on January 1, 2026
Ontario amended the Construction Act so that current section 26 contains annual release mechanics for holdback, including notice and payment timing. The current Act provides that an owner publishes a notice of annual release and contains specified timing for payment following publication. Related regulations prescribe the notice form and publication process.
This means older construction-finance explanations that describe holdback only as one amount released after project completion can be incomplete for current Ontario projects. Transitional rules can also matter for projects spanning the change. Borrowers should rely on project counsel for the actual holdback calendar.
Lien rights have short statutory deadlines that depend on the triggering facts
The current Construction Act contains 60-day preservation periods tied to specified events under section 31, and a preserved lien generally expires unless perfected within the later statutory perfection period described by section 36. Which clock applies can depend on the claimant’s role, last supply, contract completion/abandonment/termination and certificates or notices.
This page should not be used to calculate a claimant’s deadline. A borrower, contractor or lender dealing with an actual unpaid claim, registered lien or threatened lien requires immediate Ontario construction-law advice because missing the applicable date can change rights.
Mortgage priority and construction-lien priority are not a simple “first registered wins” rule
Section 78 of Ontario’s Construction Act contains specific priority rules involving liens and mortgages, including rules that can treat mortgage advances differently depending on timing and circumstances. Construction financing therefore cannot safely assume ordinary registration chronology answers every priority question.
This is one reason construction lenders rely heavily on lawyers for title searches, advance instructions and lien clearance before each material disbursement.
Each new mortgage advance can create a fresh legal-disbursement question
At the first advance, title may be clear. Weeks later, new work has been supplied, payment disputes may exist and lien rights may have arisen even if nothing is yet registered. The lender is being asked to release additional money into a changed legal environment.
Title searches, declarations and payment evidence are therefore part of draw underwriting, not merely the final discharge process.
An unregistered lien risk and a registered lien are different—but both can affect funding
A registered lien is visible on title and normally creates an immediate issue for sale, refinancing or further advances. But lien rights can exist before registration, which is why a clean title search alone may not answer every construction-payment question.
The lender and lawyer may require additional evidence about recent work, payments and statutory holdback rather than relying only on the land registry snapshot.
Payment evidence helps connect physical progress with legal clearance
Depending on the transaction, the lender or lawyer may request statutory declarations, contractor invoices, proof of payment, subcontractor information, holdback calculations, certificates/notices or other evidence before releasing funds.
The purpose is not to make the borrower prove that no future dispute is possible. It is to reduce the risk that new mortgage money is advanced while known construction obligations remain unresolved.
Statutory holdback affects contractor cash flow and therefore project liquidity
If part of each payment must remain retained under the statutory regime, the contractor/subcontractor chain may receive less immediate cash than the gross value of completed work. At the same time, the lender can have its own draw retention.
A construction cash-flow plan should therefore track gross work completed, lender advance, statutory holdback obligations, contractor payment timing and borrower cash separately. Treating the appraised progress value as cash available to trades can create a shortfall.
A lien dispute can delay a project even when the borrower believes the claim is wrong
A disputed lien can interfere with title, draws, sale or refinancing until it is resolved, discharged, vacated or otherwise dealt with through the legal process. The mortgage lender does not have to decide the merits of the construction dispute before protecting its security.
The borrower should separate two questions: Is the claim legally valid? and What must happen for the lender to continue funding? The first is legal; the second is governed by the commitment, lender risk decision and counsel.
Permanent financing can require construction-lien risk to be cleaned up even after the building looks complete
A permanent lender may require clear or acceptable title, confirmation of completion, outstanding deficiency treatment, appropriate insurance and legal opinions before paying out construction debt. An unresolved construction claim can therefore block the takeout after physical completion.
The project is not financially complete until the physical, legal and financing completion states align.
When an actual construction lien exists, legal review becomes part of the financing response
General mortgage guidance can explain holdback concepts, financing consequences and the statutory framework, but it cannot determine a claimant’s deadline, lien validity, priority, trust claim, amount owing, discharge remedy or litigation strategy from incomplete facts.
When an actual lien, notice, unpaid contractor or priority dispute exists, the borrower should obtain advice from an Ontario construction lawyer while also confirming how the issue affects the lender’s remaining draws or permanent takeout financing.
Vacating a construction lien: the title may clear while the security and funding problem remain
A construction lien can affect mortgage financing even when the owner disputes every dollar claimed. One possible legal route is to vacate its registration through a court order supported by money or security. Under the specified orders in section 44 of Ontario’s Construction Act, the lien moves from the premises and applicable holdback charges to that substituted security. The practical question is therefore not simply whether the title will look clear: it is what remains committed to the dispute after the order and whether the incoming lender accepts the resulting position. Counsel must determine the applicable procedure and evidence.
For a closing that depends on this route, put the events in an executable order: obtain the required security, obtain and implement the order, confirm the lender’s title condition, then release the advance under the approved closing arrangements. Where security must exist before the lender will advance, a plan that uses that same blocked advance to create the security has a funding gap. Ask the lawyer and lender whether an agreed alternative funding sequence is possible; do not assume an undertaking, anticipated order or application already filed satisfies their conditions. A court process can be available in principle while the proposed mortgage still cannot close on time.
Consider an illustrative file in which counsel confirms a $125,000 security requirement and the remaining construction budget is $40,000. That creates $165,000 of separate funding needs before financing costs, unless an approved arrangement changes the actual cash requirement. The $125,000 is not automatically a settlement payment to the contractor, and clearing the registration does not make it spendable again. If a security provider offers an instrument instead of a cash deposit, obtain its actual collateral, fee and release requirements; the face amount alone does not show the homeowner’s liquidity burden. This is a funding illustration, not a statutory security calculation.
Keep the continuing claim, any security facility and unfinished-work budget in the lender disclosure. The lawyer should confirm what permits eventual release or reduction of the posted security, while the mortgage adviser checks the payments and accessible reserves that remain meanwhile. A construction lien delays or prevents this closing when the legally acceptable title solution, the money needed to implement it, or lender approval cannot be delivered by the required date. Neither a disputed claim nor a possible vacating motion guarantees that financing will proceed.
Construction-lien documents: match the discharge to the premises being financed
When a lender or lawyer asks for documents about a construction lien, provide enough information to identify both the claim and the land affected: the current parcel information and registered instrument, the construction agreement and relevant changes, invoices and payment records, any claimed holdback, and the actual settlement, discharge or court material on which the proposed closing relies. The lawyer must determine what is required for this file; a receipt saying that a contractor was paid is not itself proof that the required title step has occurred. A particularly important distinction arises with a general lien covering more than one premises. Section 42 of Ontario's Construction Act permits a prescribed discharge to be registered against one or more of those premises without eliminating the lien's application to the others. Consequently, a package should identify which property is being released, which instrument is affected and what remains outstanding elsewhere. If the mortgage concerns the released property, ask the lawyer to match the release to that property's title and report whether it satisfies the lender's actual instruction. If it concerns another property, do not assume the same paper clears that title. This is a document-matching question for the closing professional, not a borrower determination that the underlying claim has disappeared.
Consider a hypothetical general lien affecting Lots A and B, with the proposed mortgage secured only on Lot B. A negotiated payment and a registered discharge referring to Lot A may be genuine and still fail to establish that Lot B is clear for the planned advance. The useful next request is therefore the correct premises-specific instrument or other legally effective resolution, followed by the lawyer's current title confirmation; another copy of the same payment receipt cannot repair the mismatch. Conversely, a valid release of Lot B should not be described as a release of the claimant's rights against Lot A unless the actual documents support that conclusion. Keep any remaining work, unpaid amounts, security and lender conditions visible in the closing statement. The existing lien-security discussion already explains that vacating a lien against security does not make the financial obligation vanish or fund that security from an advance that cannot yet occur. Here the additional check is narrower: does the purported title cure apply to the precise premises and registration being financed? Have the lawyer resolve transition rules, validity, priority and the required form of any order or registration before treating the requested documents as a completed funding condition.
Development equity: completed sale proceeds can remain committed to the contractor
Land equity can contribute to a townhouse development when the construction lender accepts the land basis, deducts relevant existing debt and states how that contribution satisfies the project’s equity requirement. Show the remaining cash separately. In a phased project, the developer may also expect completed townhouse sales to fund the next phase. The existing draw and annual-holdback analysis already prevents using the same future sale twice. Add a legal check after a sale actually closes: money received by the vendor is not necessarily unrestricted equity for another phase.
Land equity can similarly support a mixed-use development, subject to accepted land value, existing charges and the actual facility. Identify whether the proposed next-stage contribution is already owned land, fresh cash, a construction advance or proceeds from a component already sold. These amounts have different legal and financing conditions. A sale of a finished residential component does not establish that its residual proceeds can be diverted to the commercial component while amounts relating to the sold improvement remain owed. Have project counsel identify the relevant contracts, improvement, contractor and trust obligations rather than assuming a component’s completion ends the whole project’s payment duties.
Ontario Construction Act section 9 creates a vendor’s trust from sale consideration received, after the statutory deductions for reasonable sale expenses and mortgage discharge. The former owner cannot use trust property inconsistently with that trust until the amounts owed to the contractor for the improvement are paid. This is an additional inquiry even when purchaser deposits have become completed-sale proceeds and the closing’s title requirements were satisfied. The lawyer must determine the actual trust amount, permitted payments and continuing holdback obligations; a clean title search or mortgage payout alone does not prove an unrestricted surplus.
Assume counsel confirms C$450,000 of net sale proceeds within the applicable trust after the sale-expense and mortgage deductions, and confirms that C$350,000 of contractor obligations must be lawfully settled before the remaining money is free for another stage. After those obligations are properly paid and any holdback or other restriction is resolved as required, the assumed unrestricted residual is C$100,000. If the next phase needs C$300,000, it remains C$200,000 short. Counting the initial C$450,000 as immediately available would instead suggest a C$150,000 surplus. These are chosen, counsel-confirmed scenario amounts, not a statutory holdback calculation or permission to release holdback early.
For townhouse land-equity funding, put the accepted land contribution beside each actual unit-sale distribution: mortgage release, sale expenses, applicable contractor/trust payments and only then verified unrestricted proceeds. For mixed-use land-equity funding, keep the same tracing across the relevant residential and commercial contracts instead of netting all deposits and receipts into one equity figure. A creditor payment may discharge an obligation without increasing cash available to build. Ask the construction lender how it treats the remaining contribution and whether a new advance has its own trust, draw and security conditions.
If the next stage relies on the C$200,000 missing in the illustration, obtain an actual additional equity source, amended financing or a feasible revised sequence before committing the money elsewhere. A disputed contractor amount or a planned future release needs legal resolution; it should not be treated as free cash by the borrower. The existing deposit discussion covers restrictions before unit closing, while this check concerns trust obligations after receipt of sale consideration. The original land can still be valid credited equity even when those sale proceeds cannot fund the next invoice.
Sources and current-rule checks
Sources and verification
Ontario’s current Construction Act and 2026 regulations anchor the statutory discussion. The page intentionally does not calculate legal deadlines or determine lien validity/priority for a specific project; those questions require project-specific Ontario legal review.
Ontario e-Laws
Construction Act, R.S.O. 1990, c. C.30
Verified August 19, 2026
Ontario e-Laws
O. Reg. 304/18: General — Construction Act
Verified August 19, 2026
Ontario e-Laws
O. Reg. 384/25: Transitional Matters — Construction Act
Verified August 19, 2026
Financial Services Regulatory Authority of Ontario
Mortgage Product Suitability Assessment
Verified October 19, 2026